Design settings control options applicable to conductors, assemblies, structural calculations, views, voltage drops, underground and network model settings. They are accessed from the Project tab of each project.
Conductor settings
Stringing Temperature
Define the stringing temperature that applies to newly placed strain sections.
Note that changing this setting will not impact any existing conductors in the model.
To update the Defined at temperature for the strain section:
Select the strain section in the Perspective, Profile or Plan views, then navigate to the Properties panel and update the Defined at field in the Catenary Definition section
Open the StrainSection report and update the Stringing temperature field.
Default Max Operating Temperature
Defines the maximum operating temperature for strain sections and will apply to new conductors unless overridden.
See Set the Maximum Operating Temperature of a conductor for more information, including how to override the default in the Properties panel.
Per Span Equalisation Temperature
Define the temperature used when equalizing the tension of a strain section at a structure.
This only applies if a per span constraint is applied in the conductor constraint in Defined by (examples are Length Per Cable Per Span (Clip Insulators), H-Tension Per Cable Per Span, Catenary Constant Per Cable Per Span)
This feature would most commonly be used when trying to retain the existing length of a conductor, for example when inserting a new inline pole into a tension section without cutting the conductor.
It effectively unclips the insulators at the structure and reclips the insulator in a plumb position at the Per Span Equalisation Temperature.
Consider this example where there is a tension imbalance across the insulator causing the insulator to swing (to equalize the tension)
To equalize the tension at this structure select a pole and hold the shift key and select the strain section
Then click equalize
Insulators should now be plumb
Note this can impact on the insulator positions of adjacent structures
Stringing Report Start Temperature
Define the start temperature used in the built-in Stringing table CSV report.
See Quick exports with built-in reports for in-built reports.
Download the report by opening the Report tab and selecting Export stringing table CSV. Open the CSV using an app such as Microsoft Excel or Google Sheets.
Note the report will contain spans selected in the Perspective, Profile or Plan views. If none are selected then the report will cover the entire design.
Stringing Report Temperature Increment
Define the temperature increment used in the built-in Stringing table CSV report.
See Quick exports with built-in reports for in-built reports.
Download the report by opening the Report tab and selecting Export stringing table CSV. Open the CSV using an app such as Microsoft Excel or Google Sheets.
Note the report will contain spans selected in the Perspective, Profile or Plan views. If none are selected then the report will cover the entire design.
Conductor Constraint
Define the default constraint type for new strain sections as either:
Note updating this Conductor Constraint in the design settings will not change any existing conductor models.
To view or update for each strain section:
Select the strain section in the Perspective, Profile or Plan views, then navigate to the Properties panel and Defined by field in the Catenary Definition section.
Note that the Defined by field offers more options than the default in Design settings, see Catenary definition.
The default option chosen will update the name of Design setting for Tension as %CBL (below).
Stringing/Max/First Endpoint Tension as %CBL
The field name updates based on Conductor constraint selected.
Defines the cable breaking load percentage (%CBL or CBL%).
Note changing this setting will not impact any existing conductors in the model.
To update for each strain section:
Enable SRF and TSRF on New Conductors
Define whether Section Reduction Factor (SRF) and Tension Section Reduction Factor are enabled for a new strain section.
See Span Reduction Factor SRF and Tension Section Reduction Factor TSRF for more information.
Vertical Circuit Gap
Gap applied when stringing multiple circuits using the Conductor stringing tool
Consider this example where some HV has been strung and then LV is to be strung underneath with the Conductor stringing tool
Default Voltage
Define the voltage that applies for new strain sections.
To update for each strain section:
Select the strain section in the Perspective, Profile or Plan views, then navigate to the Properties panel and update the Voltage field in the Model Properties section, or
Open the StrainSection report and update the Voltage field.
Default Mzcat Terrain Category
Define the category of the span used to calculate the appropriate wind speed multiplier M(z,cat)
See M(z,cat) gust wind speed multiplier for more information.
Note that this is specific for Australia and New Zealand and may not be available in all projects. If you need assistance, please use the Help tab to Chat with support.
Gust Factor Height Calculation Method
Define the conductor height of the span used to calculate the appropriate wind speed multiplier. For each of these options it will specify the Cable Height Calculation Method which is explained underneath this section.
Options are
Default per standard
AS/NZS 7000 Synoptic:
Cable Height Calculation Method: Cable Average Ground Clearance
See M(z,cat) gust wind speed multiplier for more information.
AS/NZS 7000 Downdraft
Cable Height Calculation Method: Cable Average Ground Clearance
NESC2017
Cable Height Calculation Method: Cable Average Endpoint Height
NESC2023
Cable Height Calculation Method: Cable Average Endpoint Height
Per cable sampled average
Cable Height Calculation Method: Cable Average Ground Clearance
Per cable endpoint average
Cable Height Calculation Method: Cable Average Endpoint Height
Per cable structure attach average
Cable Height Calculation Method: Cable Average Assembly Height
Note that this applies to all spans and cannot be overridden. It will have the greatest impact for spans crossing chasms where the distance between conductor height at attachment points and at the centre of the line is significant.
Cable Height Calculation Methods
Cable Average Ground Clearance
Averages heights above ground of all conductor pieces (wires) in the span at 11 equally distant points (one point every 10% of curve including curve’s start and end points). This will capture any valleys between the structures as can be seen below.
Cable Average Endpoint Height
Averages cable start and end heights above the ground at the structures when the insulator in “No” swing conditions ("No" swing conditions assume that suspension insulators are perfectly vertical / plumb as if there were no cables attached to them)
Warning: this setting will ignore the impact of any valleys between the structures and hence could lead to underestimating the wind speed (as can be seen below).
Cable Average Assembly Height
This behaves the same as Cable Average Endpoint Height except that instead of using the insulator end point it will use where the insulator attaches to the cross arm/pole.
Warning: this setting will ignore the impact of any valleys between the structures and hence could lead to underestimating the wind speed (as can be seen below).
Note that this is specific for Australia and New Zealand and may not be available in all projects. If you need assistance, please use the Help tab to Chat with support.
Assemblies settings
Default Distance From Pole Top
Define the default distance assemblies are applied from the top of the pole.
To override this for an assembly:
Structural settings
Simple Fea Load Distribution
Define whether to use a basic non-iterative Finite Element Analysis (FEA) solve to distribute the forces between aerial stays and support between H-frame poles.
Note that the static analysis results are not affected if Is aerial stay has not been selected in StrainSections report (this may need to be added as a column).
This setting exists to allow for improved accuracy when using static analysis.
It is best practice to use FEA to get more accurate results.
If this is not available in your project and you think it should be, please use the Help tab to Chat with support.
Pole to Pole Join Threshold
Define the maximum distance that the shaft centrelines of poles can be within for a rigid element to be placed between so that these are modelled together in Finite Element Analysis (FEA) as a single unit. Note the poles need to be connected as a multi-pole for this setting to be applied.
For example if you wanted to model a brace pole supporting another pole you could use this setting.
To make the support pole take the loading it needs to have the primary pole set as the main pole.
And if the pole centres are within the Pole to Pole Join Threshold then they will be connected in the FEA model as can be seen in the FEA results below.
Removed Status Stops Loads From Being Applied
If Status field of an object (poles, assemblies, stays and conductors) is set to Removed then object is not considered in load calculations.
To set the Status field open the relevant report (i.e. Assembly report) and set status of desired objects to Removed.
For example
Where there is a strain point that has conductor Status set to Remove in the Materials tab on just one side of the pole.
Disabling this will result in a balanced loading still on this pole under no wind (assuming no line angle and equal tension and span lengths).
Enabling this will result in the conductors continuing to be seen in the Perspective view, however they will not be included in the structural analysis. Hence there will be a structural imbalance across the pole:
Removed Status Hides Objects From View
If Status field of an object (poles, assemblies, stays and conductors) is set to Removed then object is not visualised in the Perspective, Plan, and Profile views.
To set the Status field open the relevant report (i.e. Assembly report) and set status of desired objects to Removed.
Note this setting does not change any structural calculations.
View settings
Profile View - Centre Line Offset
Define the minimum half width of a corridor that is visualised in the Profile view and any objects within this corridor will be visible.
Note that the actual corridor width is the maximum of the following:
The centre line offset: a specified constant distance from the centre line.
This gives a fixed-width corridor that is the same for all sections.
The outside conductor offset: a distance beyond the far edges of the widest conductor span per section.
This gives a corridor that varies in width from section to section, but always fully contains the spans along each section.
Profile View - Outside Conductor Offset
Define the margin added to the calculated corridor half width for selected conductors that are visualised in the Profile view.
Note that the actual corridor width is the maximum of the following:
The centre line offset: a specified constant distance from the centre line.
This gives a fixed-width corridor that is the same for all sections.
The outside conductor offset: a distance beyond the far edges of the widest conductor span per section.
This gives a corridor that varies in width from section to section, but always fully contains the spans along each section.
Enable World Viewer
Define whether World Viewer is enabled in the Perspective and Plan views. This is automatically disabled if there is no terrain layer present in the design.
If this is not available in your project and you think it should be, please use the Help tab to Chat with support.
Model Graphics
Define whether to render structures as Stick or Normal with all of its dimensions and features visible in the Perspective, Plan, and Profile views.
Ground line indicator box threshold
Define the threshold above which a box indicating the ground line override will be rendered around the bottom of the pole in the Perspective view.
To override pole ground line select a pole in Perspective, Plan or Profile views, then navigate to the Properties panel and under Coordinates update G (Ground height) field.
Voltage drop settings
Voltage Drop Mode
Define the method used to calculate voltage drop estimations as either:
Simple (see Simple voltage drop)
Statistical (see Statistical voltage drop)
Note that Simple is only suitable for radial circuits (where the path from the root transformer to all connected loads is a tree) while under Statistical electrical loads are modelled as stochastic current sources, and node voltages are simply calculated via (linear) nodal analysis. This method is the preferred alternative to Simple when circuits are not radial and/or when loads are non-homogenous.
If this is not available in your project and you think it should be, please use the Help tab to Chat with support.
Voltage Drop Confidence Level
Define the number of standard deviations from the mean applied when estimating minimum node voltages under Statistical mode (above).
If this is not available in your project and you think it should be, please use the Help tab to Chat with support.
Cable Loading Confidence Level
Define the number of standard deviations from the mean applied when estimating maximum cable current using the Statistical mode (above).
If this is not available in your project and you think it should be, please use the Help tab to Chat with support.
Transformer Loading Confidence Level
Define the number of standard deviations from the mean applied when estimating maximum transformer current using the Statistical mode (above).
If this is not available in your project and you think it should be, please use the Help tab to Chat with support.
Underground settings
Trench Section Buffer Size
Define the length extending for either end of the trench section that no new section can encroach.
Where trench sections encroach on the buffer zone, overlapping (conflicting) sections are shortened or removed to ensure buffer is observed and overlap does not occur. Cables within conflicting trench sections will be rerouted.
Note that conflict resolution takes place when a new trench section is finished being placed and its start or end is within the buffer zone of an existing trench.
If this is not available in your project and you think it should be, please use the Help tab to Chat with support.
Placement Friction Formula Field
Define the name of the custom field on UgCablePlacement report from which coefficient of friction is read for the purposes of underground cable pull calculations.
Note that if the value in the field is invalid or null then section uses default friction coefficient as defined on underground cable under
cable_pull_properties.default_friction_coefficient
field.
For more information on how to create a UgCablePlacement report, see Create a custom report.
If this is not available in your project and you think it should be, please use the Help tab to Chat with support.
General settings
Units
Define whether the project uses Whether to use Metric or US Customary (Imperial) units for physical quantities.
Validation reports & in-built clearance check settings
Span Clearance Constant (k)
Defines the k constant used in the inbuilt midspan clearance checks. There are three places these checks can be found:
The second is in the SpanPairClearanceReports
To access these reports:
Create a custom report for SpanPairClearanceReports
The third is in the Validation reports.
See Span clearance calculations for more information.
Download the in-built report by opening the Report tab and selecting Export span clearance CSV. Open the CSV using an app such as Microsoft Excel or Google Sheets.
Note the report will contain spans selected in the Perspective, Profile or Plan views. If none are selected then the report will cover the entire design.
Span Clearance Constant (y)
This field does not currently alter any calculations as it is not required under the current Australian and New Zealand standards.
Span Clearance Constant (q)
Defines the q constant applied when running through-span clearance reports.
There are three places these checks can be found:
The second is in the SpanPairClearanceReports
To access these reports:
Create a custom report for SpanPairClearanceReports
The third is in the Validation reports.
See Span clearance calculations for more information.
Download the in-built report by opening the Report tab and selecting Export span clearance CSV. Open the CSV using an app such as Microsoft Excel or Google Sheets.
Note the report will contain spans selected in the Perspective, Profile or Plan views. If none are selected then the report will cover the entire design.
Factored Everyday Tension Warning Threshold
Define the maximum threshold that factored everyday tension may be before a warning occurs in the Factored everyday tension in-built report.
Attachment Lift %CBL Threshold
Define the maximum allowed uplift force for assemblies used in uplift reports.
Attachment Lift Temperature
Define the temperature used in the lift calculations within the Attach lift in-built reports.
Longitudinal Out Of Balance Tension Threshold
Define the maximum threshold that longitudinal out of balance tension may be before before a warning occurs in the Ruling span sanity check in-built report.
Upper Throughspan Environment
For spans attached to the same poles, define the environment used when calculating sag of upper span in span clashes.
Note this setting can also be modified:
There are three places these checks can be found:
The second is in the SpanPairClearanceReports
To access these reports:
Create a custom report for SpanPairClearanceReports
The third is in the Validation reports.
Download the in-built report by opening the Report tab and selecting Export span clearance CSV. Open the CSV using an app such as Microsoft Excel or Google Sheets.
Note the report will contain spans selected in the Perspective, Profile or Plan views. If none are selected then the report will cover the entire design.
Lower Throughspan Environment
For spans attached to the same poles, define the environment used when calculating sag of lower span in span clashes.
See details on Upper Throughspan Environment for more details on how this setting can be modified for individual or multiple spans within a project.
Related articles: